WisDOT Village Construction
The Wisconsin Department of Transportation (WisDOT) is planning construction efforts on STH 164 from County Q in the Village of Richfield to County E in the Town of Polk.  

The WisDOT Project Website is where you can find the most up-to-date information regarding the STH 164 construction project.

Project Details
  • Rehabilitating the existing roadway.
  • Reconstruct and safety improvements at all intersections.

164

The purpose of the proposed rehabilitation is to update pavement conditions, safety, traffic flow and to provide for adequate bicycle facilities. The WIS 164 project is approximately 7.5 miles and extends from north of County Q to north of County E, in Washington County.

Project Schedule:
Stage 1 - 2018: Anticipated start date September 17th to Late October

Complete deep marsh excavation between Pioneer Road and CTY E
Detour STH 164 for up to 30 days (CTY Q to CTY E)

Stage 2 - 2019: Anticipated start date late March

Begin construction -south project limits to STH 167 (Holy Hill Road)
Detour STH 164 (CTY Q to CTY E)

Stage 3 - 2019: Start date early June to late August

Continue construction - south project limits to STH 167
Construction of roundabout STH 167 and STH 164
Close and detour STH 167 (early June through late August)
Continue detour of STH 164 (CTY Q to CTY E)
Complete all stage 2/3 work prior to September 2019

Stage 4 - 2019: Start date early June end date late October

Construction of STH 167 to CTY E
Detour STH 164 (CTY Q to CTY E)

Project completion October 31, 2019


WisDot Press Release 9.27.2018

WisDOT 164 Roll Plot Plans from CTH Q to CTH E
Detour Plan for STH 167
Detour Plan for STH 164


WisDOT STH 164 Project Manager
Kurt Flierl 
Hubertus Office: (414) 750-3085